Overview
Techedge designs and installs distributed renewable energy (DRE) systems for Farmer Producer Organisations (FPOs), Self-Help Groups (SHGs), MSMEs and rural enterprises β from grid-tied rooftop solar to hybrid solar + battery storage and larger commercial-scale battery energy storage. We handle the full cycle: site survey, DPR preparation, grant and subsidy documentation (SELCO Foundation, AIF, DISCOM net metering), engineering, supply, installation and commissioning.
Key Benefits
- β End-to-end grant and subsidy documentation β SELCO Foundation, AIF, DISCOM net metering
- β Three proven technology lines: on-grid PV, hybrid solar + BESS, and C&I-scale battery storage
- β DPR preparation and energy assessment tailored for FPO/SHG loan and grant applications
- β 16-month average payback on grant-supported on-grid installations
- β Field-proven components β Deye BIS/IEC certified inverters, LiFePOβ batteries with 6,000+ cycle life
- β Remote monitoring and O&M support after commissioning
How It Works
Site survey & energy assessment
Techedge audits your load profile, roof/land availability and grid connection to size the right system.
DPR & grant documentation
We prepare the Detailed Project Report and handle SELCO Foundation, AIF or DISCOM documentation on your behalf.
Engineering, supply & installation
Choose the right technology line β on-grid PV, hybrid + BESS, or C&I-scale battery storage β installed and commissioned by Techedge.
Commissioning & remote monitoring
Net metering liaison, performance testing, user training, and ongoing remote monitoring / O&M support.
Ideal For
Real Project β Real Numbers
Featured Case Study
Mandprabha Farmer Producer Company, Satara β 45 kW On-Grid
Women-led millet processing unit. Techedge secured a βΉ7,64,180 SELCO Foundation grant and engineered, supplied and commissioned the system end-to-end.